Before a strong typhoon comes, conduct a comprehensive and detailed inspection of the installation of solar panels, and take preventive measures in a timely manner.
• Including screws and fasteners, whether the fasteners are fastened firmly, check if the middle and side pressure blocks of the photovoltaic power station are loose, please fasten them in time.
• For solar panels installed with hooks and fixtures, check whether the hooks and fixtures are installed securely. For a solar energy system station installed on a flat roof, the tandem modules on the windward side can be bound and fixed with double-strand 2 mm2 iron wires. For power stations with small fixed piers, sandbags can be used to increase the counterweight of the power station.
• For photovoltaic power stations without protective brackets, install and fasten windproof rods to prevent the solar panel brackets from twisting with the wind; ground power stations should tamp the ground anchors on both sides of the array.
• The roof power station should be inspected regularly to ensure the quality of the building on which the photovoltaic project is based.
If there is a special fixed problem, please contact the installer for maintenance as soon as possible!
In addition, what should be done after a typhoon passes by?
• Check the insulation and sealing of each electrical equipment in the photovoltaic power station, and check whether the AC and DC terminals are connected properly. In case of low terrain, high water level, flooding of the combiner box, etc., the ground photovoltaic power station should try to remove the on grid inverter from the site or choose a high place to place it again.
• When ascending to inspect the power station, please pay attention to personal safety during operation. Electrical inspection should be carried out by professionals with electrician qualifications, and do not touch high-voltage (DC, AC) live parts at will. When a typhoon passes through, please do not work outdoors.